《全厂照明安装方案(中英文).docx》由会员分享,可在线阅读,更多相关《全厂照明安装方案(中英文).docx(9页珍藏版)》请在优知文库上搜索。
1、全厂照明安装Installationofplantlighting施工作业指导书ConstructionMethodology作业项目名称:全厂照明安装Projectname:InstallationofPlantlighting专业:电气Specialty:Electrical2020年11月12日November12,2020目录CONTENT1 编制依据BASISOFCOMPILATION12 工程概况PROJECTGENERALSITUATION13 施工机械配置CONSTRUCTIONMECHANICALDEVICE14 人员安丹FPERSONNELARRANGE25 施工工期CON
2、STRUCTIONPERIOD26 施工方法及措施27 质量保证措施QUALITYCONTROLMEASEURES58 安全保证措施SAFETYGUARANTEEMEASURES59 文明施工CIVILIZEDCONSTRUCTION610 安全、健康/环境控制措施SAFETY,healthAndenvironmentcontrolMEASURES61编制依据Reference.浙江设计院提供的本项目的相关图纸;1.1 RelevantdrawingsofthisprojectprovidedbyZheiangDesignInstitute2 工程概况ProjectGeneralSituati
3、on2.1 本工程照明安装作业范围是全厂构筑物照明、设备照明及路灯照明。2.2 1Thelightinginstallationscopeofthisprojectisthewholeplantstructurelighting,equipmentlightingandstreetlighting.2.3 混凝土建筑内的照明管路为暗敷设,钢结构建筑及设备照明管路为明敷设。2.4 Thelightingpipelineinconcretebuildingisdarklaying,andthelightingpipelineofsteelstructurebuildingandequipmenti
4、sbrightlaying.2.5 主厂房及集控楼区域照明灯具数量为407套,2.6 ThenumberOflightingfixturesinmainplantandcentralcontrolbuildingsis407sets,2.7 其它辅助厂房257套。Otherauxiliaryfactorieslampsatotalof2422sets.2.8 230KV配电装置及网控楼照明56套。230KVDistributionInstallationandNetworkControlBuildingLightinglampsatotalof56sets.2.9 水工系统247套。Hydra
5、ulicsystemslampsatotalof247sets.2.10 水废水系统照明174套。ChemicalWaterWastewaterSystemlampsatotalof174sets.2.11 区道路照明78套PlantStreetsLightinglampsatotalof174sets.3 施工机械配置ConStrUCtiOnmachineryconfiguration50T汽机吊1台50Tenginecrane1运输车辆1台Transportvehicle1电工工具若干Electricaltools4 人员安排PersonnelArrange班长1名Monitor1技术员1
6、名Technician1组长2名2teamleaders工人20人20workers5 施工工期ConstructionPeriod计划开工日期2020年9月25日计划结束日期2021年9月25日。工期360天。PlannedstartdateSeptember25,2020,plannedenddateSeptember25,2021.Thedurationis360days.6 施工方法及措施ConstructionMethodsandMeasures6. 1构筑物照明。Structurelighting.6.1.1 暗敷设的管路跟随土建专业混凝土框架施工进度同时进行。Thehiddenl
7、ayingpipelinefollowstheconstructionprogressofcivilengineeringprofessionalconcreteframeatthesametime.6.1.2 明敷设的管路,首先确定管路的走向,然后用角钢与U型卡子制作固定卡子,焊接于相应位置再将照明钢管用卡子固定。最后安装照明盒。First,thedirectionofthepipelineisdetermined,thenthefixedclipismadewithanglesteelandUclip,weldedinthecorrespondingpositionandthenfixed
8、withclip.Finallyinstallthelightingbox.6.1.3 灯具的安装,根据图纸设计选择正确型号的灯具并将灯具安装于图纸中设计的位置。Installationoflamps,selectthecorrecttypeoflampsaccordingtothedrawingdesignandinstallthelampsinthedesignpositioninthedrawing.6.1.4 照明箱的安装,根据图纸设计选择照明箱,保证箱内开关容量与数量正确。然后按照图纸设计将照明箱安装于正确位置。Installationoflightingbox,selectligh
9、tingboxaccordingtodrawingdesigntoensurethecorrectswitchcapacityandquantityinthebox.Theninstallthelightingboxinthecorrectpositionaccordingtothedrawingdesign.6.1.5 照明线敷设,根据图纸设计的照明灯具数量,开关位置确定每根管路中所需要的照明线根数,然后统一穿入,最后将各处接头接好并用高压防水胶布包绝缘再用低压绝缘自粘带固定。照明线规格按照设计为照明回路2.5mm2.插座回路40而。锅炉本体比较特殊,全部为4mmLightinglinela
10、ying,accordingtothenumberoflightinglampsdesignedbythedrawing,switchpositiontodeterminethenumberoflightinglinesneededineachcanal,andthenunifiedpenetration,Finally,thejointsareconnectedandinsulatedwithhighvoltagewaterprooftapeandfixedwithlowvoltageinsulationself-adhesivetape.Lightinglinespecificationa
11、ccordingtodesignlightingcircuit2.5mm2,socketcircuit4mm2.Boilerbodyisspecial,all4mm2.6.1.6通电试验,首先对安装完的回路用500V绝缘电阻测试仪进行绝缘试验,绝缘电阻不小于0.2MC。合上全部的照明箱内开关,对每个回路的灯具进行检查是否正常运行。Powertest,firstofall,theinstalledcircuitwith500Vinsulationresistancetesterinsulationtest,insulationresistanceisnotlessthan0.2M.Closeal
12、ltheswitchesinthelightingboxandcheckthenormaloperationofeachcircuitlamp.6.2设备照明EqUiPmentlighting6.2.1明敷设的管路,首先确定管路的走向,然后用角钢与U型卡子制作固定卡子,焊接于相应位置再将照明钢管用卡子固定。最后安装照明盒。如果照明部分与主设备为厂家成套,根据厂家图纸设计进行照明管路的敷设。First,thedirectionofthepipelineisdetermined,thenthefixedclipismadewithanglesteelandUclip,weldedinthecorr
13、espondingpositionandthenfixedwithclip.Finallyinstallthelightingbox.Ifthelightingpartandthemainequipmentarecompletesets,accordingtothemanufacturer,sdrawingsdesignlightingpipelinelaying.6.2.2灯具的安装,根据图纸设计选择正确型号的灯具并将灯具安装于图纸中设计的位置。Installationoflamps,selectthecorrecttypeoflampsaccordingtothedrawingdesign
14、andinstallthelampsinthedesignpositioninthedrawing.1.1.1 2.3照明箱的安装,根据图纸设计选择照明箱,保证箱内开关容量与数量正确。然后按照图纸设计将照明箱安装于正确位置。Installationoflamps,selectthecorrecttypeoflampsaccordingtothedrawingdesignandinstallthelampsinthedesignpositioninthedrawing.6.2.4 照明线敷设,根据图纸设计的照明灯具数量,开关位置确定每根管路中所需要的照明线根数,然后统一穿入,最后将各处接头接好并
15、用高压防水胶布包绝缘再用低压绝缘自粘带固定。照明线规格按照设备照明厂家设计为准。Lightinglinelaying,accordingtothenumberoflightinglampsdesignedbythedrawing,switchpositiontodeterminethenumberoflightinglinesneededineachcanal,andthenunifiedpenetration,Finally,thejointsareconnectedandinsulatedwithhighvoltagewaterprooftapeandfixedwithlowvoltage
16、insulationself-adhesivetape.Lightinglinespecificationsaccordingtotheequipmentlightingmanufacturerdesign.6.2.5 通电试验,首先对安装完的回路用500V绝缘电阻测试仪进行绝缘试验,绝缘电阻不小于0.2MQ。合上全部的照明箱内开关,对每个回路的灯具进行检查是否正常运行。Powertest,firstofall,theinstalledcircuitwith500Vinsulationresistancetesterinsulationtest,insulationresistanceisnotlessthan0.2MQ.Closealltheswitchesinth